[ARCHIVED] US 33 & East State Street Project Update

Logo for Engineering and Public Works Department for the City of Athens, OH


The US 33 & East State Street Project includes improvements to 2.96 miles of East State Street by adding an additional left turn lane, new sidewalk along the south side of the street (East Park Drive to Lowe's), signal improvements, milling and resurfacing, concrete joint repair, and pavement marking improvements.  The US 33 ramp improvements include lighting improvements, adding an additional right turn lane onto East State Street and adding an additional receiving lane on US 33.  An exhibit of the project can be viewed on the City's website: https://www.ci.athens.oh.us/DocumentCenter/View/4009.

Freedom Construction Enterprises, Incorporated, the Contractor for the US 33 & East State Street Project, is expected to begin preliminary activities in February and fully mobilize to the project area in early March.

The project will be managed in phases. During each phase, the Contractor will maintain residential, business, pedestrian, and emergency traffic.  Please note that the schedule is subject to change based on weather, or other unforeseen circumstances.  Regular project updates will be posted on the City's website: www.ci.athens.oh.us.

Preliminary Activities

  • Pothole patching on East State Street is planned for February.  The Contractor is coordinating the early opening of an asphalt plant to provide hot-mix asphalt for the patching.  This activity is weather dependent. 


Phase 1

  • Mobilization to the site will begin in early March. The Contractor will begin installing conduit for lighting and signals, and will begin sidewalk work.
  • Joint Repairs on the concrete roadway (approximately from Cook Drive to East State Street Access Road) are scheduled between March and April.
  • Milling and resurfacing between Utah Place and Cook Drive is scheduled for the end of May to early June. Either Temporary or Permanent Pavement Markings will be installed after the street is resurfaced.
  • Traffic Impacts: Single lane closures are allowed, access to side streets and businesses will be maintained. The contractor is reviewing night paving. No work on East State Street is permitted on Saturdays.

Phase 2

  • Signalization and lighting work will continue.
  • The Contractor will be allowed to close the US 33 WB off-ramp, and US 33 WB on-ramp (ramps by Applebee's) for 45 days. The Contractor currently has this work scheduled between early June and late July. Traffic will be detoured via the Stimson Avenue exit.
  • This phase also includes work on the US 33 EB on-ramp (ramp by Bob Evans). Temporary pavement will be installed to maintain traffic.
  • Traffic Impacts: Single lane closures are allowed, access to side streets and businesses will be maintained. The ramp closures are allowed for 45 days. No work on East State Street is permitted on Saturdays.

Phase 3

  • Signalization and lighting work will be completed.
  • Work on the US 33 EB on-ramp will be completed.
  • A truck detour will be installed.
  • The Contractor will complete the median work between Home Street and Utah Place.
  • Milling and resurfacing between Home Street and Utah Place will be completed in the fall (currently scheduled for September). Permanent Pavement Markings will be installed after the street is resurfaced.  
  • Traffic Impacts: Single lane closures are allowed, access to side streets and businesses will be maintained. The contractor is reviewing night paving. No work on East State Street is permitted on Saturdays.

As part of this project, Freedom Construction Enterprises, Incorporated, will be employing a Community Liaison.  The Community Liaison will assist the Contractor with maintenance of traffic activities, and coordinate with businesses and residents during construction activities.

We appreciate your cooperation with this worthwhile project. Questions or concerns may be directed to the City of Athens Engineering and Public Works Department, 740-593-7636. Please also watch the City website, www.ci.athens.oh.us, for project updates.

Facebook Twitter Email

Other News in Engineering and Public Works

West Union Street Improvements Project

Posted on: September 20, 2023
Leaf Pickup Map 2023

2023 Leaf Pick-up Schedule and Map

Posted on: September 11, 2023