AEP will be working in the area of the Carpenter Street, State Street, and Stimson Avenue intersection February 25 - 26, to reconfigure utility poles in this area. The work will require temporary lane closures while overhead work is completed. Overhead work in this intersection, and on East State Street, will continue the week of March 1.
AEP will also be continuing underground work between 15 West Stimson Avenue and 5 West Stimson Avenue. The work will continue on Saturday, February 27th between 10 AM – 10 PM, and Sunday, February 28th between 8 AM – 8 PM. The work is expected to be completed by mid-March, and will resume to normal working hours beginning March 1.
Questions may be directed to the Engineering and Public Works Department, 740-593-7636.