2015 Sidewalk Repair
The City of Athens has secured York Paving to complete the 2015 Sidewalk Repair Project. The project includes removing and replacing damaged sections of sidewalk on Central Avenue (Second Street to West State Street), North Congress (Woodward Avenue to West Washington Street), and South May Avenue (East State Street to Morris Avenue).
The updated schedule for the project is below:
• Central Avenue work is expected to occur between August 17 and August 27, 2015.
• North Congress work is expected to occur between August 27 and September 25, 2015.
• South May work is expected to occur between September 28 and October 23, 2015.
During construction, there may be times when sections of the roadway will be flagged for traffic. On-street parking may also be prohibited adjacent to the construction zone.
Questions or concerns may be directed to the City of Athens Engineering and Public Works Department, 740-593-7636.