Shelly and Sands, Contractor for the Richland Avenue project, is planning the following activities for the week of August 24:
• Sidewalk and concrete work will continue.
• Base course paving is expected to occur on Monday/Tuesday, with intermediate course paving expected to occur on Wednesday. Traffic will be maintained via flaggers.
• The installation of light pole foundations will continue.
Questions or concerns may be directed to the City of Athens Engineering and Public Works Department, 740-593-7636.