Shelly and Sands, Contractor for the Richland Avenue project, is planning the following activities for the week of September 28:
• Pavement Marking installation between Dairy Lane and Canterbury Drive is expected to continue through Monday or Tuesday (9/28 or 9/29). During pavement marking activities, traffic will be controlled via flaggers.
• Sidewalk work between Canterbury Drive and Pomeroy Road will continue throughout the week. Traffic will be controlled in this section via flaggers.
• Grading work will continue.
Questions or concerns may be directed to the City of Athens Engineering and Public Works Department, 740-593-7636.