Richland Avenue South Improvements Project - Update
Shelly and Sands, Contractor for the Richland Avenue project, will be raising manholes on Thursday October 8, in the southbound lane beginning at Dairy Lane. The work requires a southbound lane restriction around each manhole until the concrete is set. The lane restrictions will be cleared on Friday morning and will not impact homecoming weekend traffic. The work will continue next week.
Other activities include grading work and cleanup work. Sidewalk work is expected to continue next week.