Richland Update
Shelly and Sands, Contractor for the Richland Avenue project, is planning the following activities for the week of October 12:
• Manhole work will continue - the work will include minor lane restrictions.
• Grading work will continue in preparation for seeding - seeding is expected to occur Thursday and Friday.
• Cleanup work will continue.
• Sidewalk work between Canterbury Drive and Pomeroy Road will continue.
Frontier Communications will also be working on Richland Avenue, between Greenbrier Drive and Hocking Valley Bank, to replace an underground cable line. There may be times when traffic will be flagged through their work zone.
Questions or concerns may be directed to the City of Athens Engineering and Public Works Department, 740-593-7636.