The City of Athens Engineering & Public Works Department has contracted with Nuko Paving to complete the 2017 Street Improvements, which will include milling, paving, and crack sealing.
Pavement milling is the removal of sections of old pavement with a grinder in order to ensure new pavement is placed at the proper elevation.
The tentative milling and paving schedule is as follows:
Milling Schedule
Charles Street from East State Street to Pleasantview Drive: July 17, 2017
Old Coach from Longview Heights to #67: July 17, 2017
Avon Place from E. State Street to Sells Park: July 17, 2017
West State Street from N. Shafer Street to West State Street Park: July 18, 2017
Byard Street from N. Shafer Street to Smith Street: July 18, 2017
Pratt Street from Byard Street to W. Washington Street: July 18, 2017
Second Street from Curran Drive to Columbus Road/N. Lancaster: July 19, 2017*
Mound Street from W. Carpenter Street to Pine Place: July 19, 2017
Stewart Street from Mill Street to E. Union Street: July 19, 2017
Canterbury Drive from Mulligan to Lamar: July 20, 2017
Farhills Drive from Pomeroy Road for a distance of 1140-feet: July 20, 2017
*Milling date is dependent on concrete work completion
Paving Schedule
Cash Lane from S. Blackburn Road for a distance of 750-feet: July 20, 2017
Kenny Drive from end of concrete for a distance of 375-feet: July 20, 2017
Gibson Road from W. Union Street to Elliotsville Road: July 20, 2017
Charles Street from East State Street to Pleasantview Drive: July 21, 2017
Stonybrook Drive from Utah Place to end: July 21, 2017
Tulane (western side) from East State St. to McGuffy Lane: July 21, 2017
Woodside Drive from Cable Lane to McGuffey Drive: July 21, 2017
Old Coach from Longview Heights to #67: July 21, 2017
West State Street from N. Shafer Street to West State Street Park: July 24, 2017
Second Street from Curran Drive to Columbus Road/N. Lancaster: July 24, 2017
Roosevelt Drive from Highland Avenue to Columbia Avenue: July 24, 2017
Mound Street from W. Carpenter to Pine Place: July 24, 2017
Byard Street from N. Shafer Street to Smith Street: July 25, 2017
Pratt Street from Byard Street to W. Washington Street: July 25, 2017
Playground Drive from Mill Street to Stewart Street: July 25, 2017
Putnam Drive from Mill Street to Playground Drive: July 25, 2017
Stewart Street from Mill Street to E. Union: July 25, 2017
Canterbury Drive from Mulligan to Lamar: July 26, 2017
Farhills from Pomeroy Road for a distance of 1140-feet: July 26, 2017
Avon Place from E. State Street to Sells Park: Completed late fall, after the waterline project
One lane of traffic will be maintained, however, motorists are encouraged to avoid the work areas.
Parking on the street will not be allowed during the scheduled work. On-street parking will be removed 24 hours in advance of work days.
This schedule is subject to change in the event of inclement weather or other unforeseen circumstances. Schedule updates for the project will be posted regularly on the City of Athens website (www.ci.athens.oh.us).
Please direct questions to the Engineering and Public Works Department at 740-593-7636.