The City of Athens Engineering & Public Works Department has contracted with Nuko Paving to complete the 2017 Street Improvements, which will include milling, paving, and crack sealing.
Pavement milling is the removal of sections of old pavement with a grinder in order to ensure new pavement is placed at the proper elevation.
The tentative paving schedule will begin Saturday July 29th, 2017.
Paving Schedule:
July 29, 2017: Budget Host Drive, Gibson Road, Kenny Drive
July 31, 2017: Canterbury Drive
August 1, 2017: Farhills Avenue, Old Coach Road
August 4, 2017: Charles Street, Stonybrook Drive, Tulane Road, Woodside Drive
August 5, 2017: Roosevelt Drive, Mound Street
August 7, 2017: Second Street, Pratt Street, Byard Street
August 8, 2017: West State Street
August 9, 2017: Putnam Drive, Playground Drive, Stewart Road
One lane of traffic will be maintained, however, motorists are encouraged to avoid the work areas.
Parking on the street will not be allowed during the scheduled work. On street parking will be removed 24 hours in advance of work days.
This schedule is subject to change in the event of inclement weather or other unforeseen circumstances. Schedule updates for the project will be posted regularly on the City of Athens website (www.ci.athens.oh.us).
Please direct questions to the Engineering and Public Works Department at 740-593-7636.