Engineering and Public Works

Posted on: September 12, 2018

[ARCHIVED] 2018 Street Improvements Schedule 9/17/18 - 9/21/18

Logo for Engineering and Public Works Department for the City of Athens, OH




The City of Athens Engineering & Public Works Department will continue the 2018 Street Improvements Project, which includes milling, paving, and crack sealing of various streets within the City.


Below is the schedule for week five of paving/milling:


September 17, 2018                   Northwood Drive – Columbia Avenue to the dead end

September 18-19, 2018             Spring Street – Madison Avenue to Franklin Avenue

September 20-21, 2018             Hillcrest Drive – Charles Street to the dead end


This schedule is subject to change in the event of inclement weather or other unforeseen circumstances.


One-way traffic will be maintained with flaggers; however, motorists are encouraged to avoid the work areas.


Parking on the street will not be allowed during the scheduled work. On street parking will be removed 24 hours in advance of work days. Please direct questions to the Engineering and Public Works Department at 740-593-7636.

Facebook Twitter Email

Other News in Engineering and Public Works

West Union Street Improvements Project

Posted on: September 20, 2023
Leaf Pickup Map 2023

2023 Leaf Pick-up Schedule and Map

Posted on: September 11, 2023