[ARCHIVED] 2012 Street Improvements Project

2012 Street Improvements Project
York Paving Company has completed milling and will continue paving throughout August.

The schedule to complete the 2012 Street Improvements Project is as follows:

Street/Area Paving
Lamar from Canterbury to the dead end August 15/16
Canterbury from Richland to Lamar August 17/20
Grosvenor from Carpenter to Madison August 21/22
Utah from E. State to Hillcrest August 23
Jacobs from Strathmore to Utah August 24
Raymond from Clark to Second August 27
Currier from #34 to end August 27
Fairview from Woodward to end August 28
Woodward from Highland to N. Congress August 29
Dorr Lane from Columbus to bottom of hill August 30
Bolleana Place from Morris to Grant August 31
Fort from Grosvenor to N. Congress Expected to occur in September, after the boulder removal is complete.

This schedule is subject to change in the event of inclement weather or other unforeseen circumstances. One lane of two-way traffic will be maintained, however, motorists are encouraged to avoid the area. Parking on the street will not be allowed during the scheduled work.

Direct questions to the Engineering and Public Works Department at 593-7636.