The City of Athens Engineering & Public Works Department will continue the 2018 Street Improvements Project, which includes milling, paving, and crack sealing of various streets within the City.
Below is the schedule for week eight of paving/milling:
Milling
October 8th, 2018 Columbia Avenue
Columbus Road
Paving
October 3rd, 2018 South May Avenue
October 4th, 2018 South May Avenue
October 5th, 2018 South May Avenue
October 8th, 2018 Columbus Road
October 9th, 2018 Columbus Road
October 10th, 2018 Columbia Avenue
October 11th, 2018 Columbia Avenue
October 12th, 2018 Columbia Avenue
This schedule is subject to change in the event of inclement weather or other unforeseen circumstances.
One-way traffic will be maintained with flaggers; however, motorists are encouraged to avoid the work areas.
Parking on the street will not be allowed during the scheduled work. On street parking will be removed 24 hours in advance of work days. Please direct questions to the Engineering and Public Works Department at 740-593-7636.