The Contractor for the East State Street Project is scheduled to begin pavement marking work on the US 33-50 on-ramp, between Home Street and Strathmore Boulevard, and between Cook Drive and Della Drive, on Sunday, December 2. The pavement marking work is expected to be completed on Monday, December 3.
Traffic will be reduced by one lane in each direction while work is completed, and traffic may be directed by flaggers.
Questions may be directed to the City of Athens Engineering & Public Works Department, 740-593-7636.