Trucco Construction will continue work in January on the Stimson Avenue project.
During the week of January 4, the Contractor expects to begin work installing a sanitary sewer main on Stimson Avenue, between Grant Street (North) and Palmer Street. They will also begin work on water valve installation throughout the corridor.
Traffic will be maintained on Stimson Avenue by use of the center lane, and by flaggers.
The following lane closures, or intersection closures, on side streets will also be in place:
- January 4 and 5, 2021 - Kern Street, Palmer Street, North Campbell Street, and Elliot Street:
- One Lane will be closed during the day with flaggers. Both Lanes will be open at the end of the day.
- January 6 and 7, 2021 - North Campbell Street and Elliot Street:
- One Lane will be closed during the day with flaggers. Both Lanes will be open at the end of the day.
- January 4, 5, and 6, 2021 - Grant Street (North):
- The Grant Street (North) intersection with Stimson Avenue will be closed each day, and re-opened each evening.
Questions may be directed to the Engineering and Public Works Department, 740-593-7636.