The paving schedule for the week of July 29th is as follows:
Street/Area Paving
Morris Avenue from E. State to May July 29 & 30
Watt Street from Sunnyside to Ohio July 31
Evans Street from Franklin to E. State July 31
Hanlin Avenue from Slaughter to N. Shafer July 31
N. Shafer Street from W. State to Rardin Aug 01
W. Washington Street from Pratt to Shafer Aug 01
This schedule is subject to change in the event of inclement weather or other unforeseen circumstances. One lane traffic will be maintained, however, motorists are encouraged to avoid the area. Parking on the street will not be allowed during the scheduled work.
Direct questions to the Engineering and Public Works Department at 593-7636.