The City of Athens Engineering & Public Works Department has contracted with York Paving Company, Inc. to complete the 2013 Street Improvements, which will include milling, paving, and crack sealing.
Crack sealing will occur tomorrow, Wednesday, July 31st, for the following areas:
• APD Parking Lot
• Verona
• Lloyd
• Ohio
• Wallace
• Maplewood
• Palmer
• Granville
• Mary
• Altamonte
• Shafer
• W. Union
• Carriage Hill
• Washington
• Pomeroy
• Richland
This schedule is subject to change in the event of inclement weather or other unforeseen circumstances. One lane traffic will be maintained, however, motorists are encouraged to avoid the area. Parking on the street will not be allowed during the scheduled work.
Direct questions to the Engineering and Public Works Department at 593-7636.