York Paving is expected to begin Columbus Road work on Monday, September 16. Activities will include shoulder grading along Columbus Road and sawcutting for the installation of the median. Traffic will be maintained on Columbus Road during these activities, but flaggers will be present. The work for these activities is expected to be completed by September 20.
York Paving will also continue work on the N. Lancaster Street waterline installation. Activities are expected to include testing and installation of new service lines. During service line installation N. Lancaster Street may be reduced to one-lane adjacent to the work zone and two-way traffic will be maintained by flagging.