York Paving Company will continue paving throughout August.
The schedule to complete the 2012 Street Improvements Project is as follows:
Street/Area Paving
Grosvenor from Carpenter to Fort August 28
Bolleana Place from Morris to Grant August 28
Fairview from Woodward to end August 29
Woodward from Highland to N. Congress August 29
Dorr Lane from Columbus to bottom of hill August 30
Fort from Grosvenor to N. Congress In Sep, after boulder removal is complete
This schedule is subject to change in the event of inclement weather or other unforeseen circumstances. One lane of two-way traffic will be maintained, however, motorists are encouraged to avoid the area. Parking on the street will not be allowed during the scheduled work.
Direct questions to the Engineering and Public Works Department at 593-7636.