Engineering and Public Works

Posted on: July 13, 2015

[ARCHIVED] Richland Avenue South Project Update

Shelly and Sands will continue work this week on the west side of Richland Avenue. Scheduled activities for the week include sidewalk and pavement removal, stormline installation, and conduit installation for the decorative lights. Utility companies will also be working on utility relocations.

Questions or concerns may be directed to the City of Athens Engineering and Public Works Department, 740-593-7636. Regular project updates will be available on the City of Athens webpage: www.ci.athens.oh.us.